Free sample questions

Twelve questions. Answer key included.

Written fresh from the public 2020 Scrum Guide — never drawn from the live exam. Every question carries its answer and a one-line explanation.

Answer key

Questions, answers, why.

01

Who is responsible for sizing Product Backlog items?

  • A. The Product Owner, who estimates on behalf of the Developers
  • B. The Developers who will be doing the work
  • C. The Scrum Master, who facilitates estimation sessions
  • D. The organisation, through a central planning office

Answer: B. Sizing belongs to the Developers who will do the work; the Product Owner may only influence it by helping them weigh trade-offs.

Take the exam — free
02

Who creates the Sprint Goal, and by when must it be finalised?

  • A. The Product Owner drafts it before Sprint Planning begins
  • B. The Scrum Master, within the first Daily Scrum of the Sprint
  • C. The whole Scrum Team collaborates on it during Sprint Planning, and it must be finalised before that event ends
  • D. The Developers, once the first items are pulled into the Sprint

Answer: C. Sprint Planning topic one ends with the whole team agreeing a Sprint Goal, finalised prior to the end of Sprint Planning.

Take the exam — free
03

How many Increments may be created within a single Sprint?

  • A. Exactly one, released at the Sprint Review
  • B. Multiple Increments may be created within a Sprint
  • C. One per Developer per week
  • D. None until the Definition of Done is rewritten

Answer: B. The Guide allows multiple Increments within a Sprint — their sum is presented at the Sprint Review, and any one may be delivered earlier.

Take the exam — free
04

An organisation has no Definition of Done of its own. What must the Scrum Team do?

  • A. Create a Definition of Done appropriate for the product
  • B. Use the Definition of Done of the largest Scrum Team
  • C. Skip it until the first production incident
  • D. Let each Developer define their own standard

Answer: A. If the organisation has no standard, the Scrum Team must create one appropriate for the product — the Developers are required to conform to it.

Take the exam — free
05

How does someone get a change into the Product Backlog?

  • A. By raising it at the Sprint Retrospective for the team to vote on
  • B. By asking the Scrum Master to reorder the backlog directly
  • C. By trying to convince the Product Owner, who orders the backlog
  • D. By editing the backlog themselves, then informing the team

Answer: C. The Product Owner orders the work; the Guide says those wanting to change the Product Backlog do so by trying to convince the Product Owner.

Take the exam — free
06

A Developer wants to re-plan the rest of the day's work after the Daily Scrum. Is this allowed?

  • A. No — the Daily Scrum plan is locked until the next day
  • B. Yes — the Daily Scrum is not the only time Developers may adjust their plan
  • C. Only if the Scrum Master approves the change
  • D. Only if the Sprint Goal is formally amended

Answer: B. The Guide states the Daily Scrum is not the only time Developers are allowed to adjust their plan; they often meet again during the day.

Take the exam — free
07

Where should the Scrum events optimally be held?

  • A. In separate tools so each event has its own record
  • B. Wherever the most senior stakeholder is available
  • C. At the same time and place, to reduce complexity
  • D. Remotely, so attendance is never missed

Answer: C. The Guide recommends that, optimally, all events are held at the same time and place to reduce complexity.

Take the exam — free
08

Under what condition are Product Backlog items deemed ready for selection in Sprint Planning?

  • A. When they can be Done by the Scrum Team within one Sprint
  • B. When they carry a signed-off estimate from management
  • C. When they have been refined three times
  • D. When the Product Owner marks them as mandatory

Answer: A. Items that can be Done by the Scrum Team within one Sprint are deemed ready for selection.

Take the exam — free
09

What does lean thinking contribute to Scrum?

  • A. It mandates six Sigma variance limits on the Increment
  • B. It reduces waste and focuses on the essentials
  • C. It replaces empiricism when the data is incomplete
  • D. It requires a separate lean event in each Sprint

Answer: B. Scrum is founded on empiricism and lean thinking; lean thinking reduces waste and focuses on the essentials.

Take the exam — free
10

How does the Guide describe the Product Goal?

  • A. A long-term objective that serves as a target for the Scrum Team to plan against
  • B. The ordered list of everything needed to improve the product
  • C. The single objective for the Sprint, created in Sprint Planning
  • D. A forecast of delivery dates published to stakeholders

Answer: A. The Product Goal describes a future state of the product and is the long-term objective the team plans against; it lives in the Product Backlog.

Take the exam — free
11

What is Product Backlog refinement, according to the Guide?

  • A. A formal re-estimation of every item at the start of each Sprint
  • B. A meeting owned by the Scrum Master and timeboxed to one hour
  • C. The ongoing act of breaking down and further defining items into smaller, more precise items
  • D. The process of moving done items into the archive

Answer: C. Refinement is an ongoing activity that adds details such as description, order and size — not a fixed Scrum event.

Take the exam — free
12

What happens if a Scrum Team fails to operate the Scrum events as prescribed?

  • A. The Sprint is automatically cancelled
  • B. The team loses opportunities to inspect and adapt
  • C. The framework reverts to the previous Sprint configuration
  • D. Nothing — the events are optional in complex environments

Answer: B. The Sprint is the container for all other events, designed to enable transparency; failing to run them as prescribed costs inspect-and-adapt opportunities.